File #: CONS 15-306   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 11/3/2015 Final action:
Subject: Pavement Rehabilitation Gas Tax FY15: Amend Construction Contract
Attachments: 1. Attachment I Resolution Amend Contract, 2. Attachment II Resolution Appropriation of Funds
DATE: November 3, 2015

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title
Pavement Rehabilitation Gas Tax FY15: Amend Construction Contract

End
RECOMMENDATION
Recommendation

That Council adopts the attached resolutions (Attachments I and II):

1. Amending the construction contract with Graham Contractors, Inc., by increasing the Administrative Change Order amount from $102,000 to $156,784 for the Pavement Rehabilitation Gas Tax FY15 project; and

2. Appropriating an additional $17,421 for this project from the Gas Tax Fund.

Body
BACKGROUND

On June 17, 2014, Council awarded the contract for the Pavement Rehabilitation Gas Tax FY15 project to Graham Contractors, Inc., and increased the Administrative Change Order amount from $40,000 to $102,000. The request for additional funds was to slurry seal additional streets that otherwise would not be included due to limited funds.

DISCUSSION

The previous Council-approved increase in the Administrative Change Order amount for additional slurry seal covered Harder Road, West A Street, and Golf Course Road. Additionally, staff included slurry seal of portions of the Police Administration Building parking lots. At that time, staff assumed the available balance from the low bid would allow for the additional streets to be completed. However, work quantities, specifically, localized pavement repairs and damaged detector loop replacement, exceeded the assumed quantities. As a result, the final construction cost exceeded the contract amount by $54,784.

As referenced in Attachment I, staff recommends Council approve the resolution increasing the Administrative Change Order amount by $54,784, for a contract total not-to-exceed amount of $873,396.

FISCAL IMPACT

The project costs are as follows:

The Adopted FY 2016 Capital Improvement Program includes $1,000,000 for the Pavement Rehabilitation Gas Tax FY15 project...

Click here for full text