DATE: April 28, 2020
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt a Resolution Authorizing the City Manager to Amend the Construction Contract with Con-Quest Contractors, Inc., for Additional Administrative Change Order Authority in the Amount of $150,000 for a Contract Not-to-Exceed $1,976,600, for the Recycled Water Customer Onsite Conversions Project, Project No. 07507
End
RECOMMENDATION
Recommendation
That Council adopts a resolution (Attachment II) authorizing the City Manager to amend the construction contract with Con-Quest Contractors, Inc., for additional administrative change order authority in the amount of $150,000 for a total contract not-to-exceed amount of $1,976,600.
End
SUMMARY
The City’s Recycled Water Project consists of constructing a treatment facility, storage tank, and pump station at the City’s Water Pollution Control Facility (WPCF) and installing distribution pipelines and customer connections to deliver recycled water to customers for irrigation and industrial uses. In September 2019, the City entered into a construction contract with Con-Quest Contractors, Inc., (Con-Quest) for the Recycled Water Customer Onsite Conversions Project. Staff is requesting Council approval to amend the construction contract amount with Con-Quest to increase the administrative change order amount by $150,000 to a total of $237,000, thereby raising the total contract not-to-exceed amount to $1,976,600.
ATTACHMENTS
Attachment I Staff Report
Attachment II Resolution