Subject: Adopt a Resolution Awarding a Contract to DeSilva Gates Construction LP for the FY20 Pavement Improvement Project, Project No. 05222, 05224, 05226, 05232, 05289, in an Amount of $9,406,497, and authorizing the Public Works Director to spend up to $11,000,000 for Total Construction Costs
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III List of Streets, 4. Attachment IV Map
DATE: May 19, 2020

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title

Adopt a Resolution Awarding a Contract to DeSilva Gates Construction LP for the FY20 Pavement Improvement Project, Project No. 05222, 05224, 05226, 05232, 05289, in an Amount of $9,406,497, and authorizing the Public Works Director to spend up to $11,000,000 for Total Construction Costs

End
RECOMMENDATION
Recommendation

That Council approves Addendums No. 1, 2, & 3 consisting of revisions to the plans and specification for the FY20 Pavement Improvement Project, and adopts a resolution (Attachment II) awarding the contract for the project to DeSilva Gates Construction LP, in an amount not-to-exceed $11,000,000.
End

SUMMARY

The FY20 Pavement Improvement Project calls for the rehabilitation of fifty-nine street sections and preventive maintenance of fifty-two street sections for a total of 111 street sections (Attachment III). This project will pave forty-two lane-miles of streets. Overall, the City is responsible for the maintenance of 657 lane-miles of roadway. The proposed improvements will repair failed pavement sections and improve street surfaces.

On April 14, 2020, the project received seven bids. All but one bid was over the engineer's estimate. At $9,406,497, the low bid received is $650,503 or 6.5% below the engineer's estimate and provides an opportunity to add other street sections to take advantage of the available budget and reasonable unit prices. Staff will use the cost savings to include additional streets to the project.

Staff recommends award of contract to the responsible low bidder, DeSilva Gates Construction LP, in the amount of $11,000,000, including potential administrative change order.

The project budget of $12,045,000 is funded via the Gas Tax, Measure B, Measure BB,
Vehicle Registration Fees, and anticipated Road Repair and Accountability Act (RRAA) (SB1) funds.



At the January 22, 2020 Council Infrastr...