Subject: Adopt a Resolution Awarding a Contract to Joe's Landscape Concrete Inc., in an Amount Not-to-Exceed $439,916 for the FY20 Sidewalk Rehabilitation Project in Districts 4, 5, 7 and 10, Project Number 05285
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Bid Results

DATE:      July 28, 2020

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT                     

Title                      

 

Adopt a Resolution Awarding a Contract to Joe’s Landscape Concrete Inc., in an Amount Not-to-Exceed $439,916 for the FY20 Sidewalk Rehabilitation Project in Districts 4, 5, 7 and 10, Project Number 05285        

                                                    

End
RECOMMENDATION

Recommendation

 

That Council adopts a resolution (Attachment II) awarding the construction contract to Joe’s Landscape Concrete Inc. in the amount of $439,916 for the FY20 Sidewalk Rehabilitation Project No. 05285.

End

 

SUMMARY

 

On June 16, 2020, the City received nine (9) bids for the project ranging from $439,916 to $767,936.20 (Attachment V).  Joe’s Landscape Concrete Inc., of Newman, submitted the low bid in the amount of $439,916, which is 10% higher than the Engineer’s Estimate of $398,500. Villalobos & Associates of Campbell submitted the second lowest bid in the amount of $441,866, which is 11% higher than the Engineer’s Estimate.

 