Subject: Adopt a Resolution Approving Addendum No. 1, Authorizing the City Manager to Award a Construction Contract to FBD Vanguard Construction, Inc., in the Amount of $801,832, Approving an Administrative Construction Contingency of $80,183; and Appropriating Additional Funds in the Amount of $141,000 for the South Hayward Safe Routes for Seniors Project, Project No. 05323
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      November 17, 2026

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works & Utilities

 

SUBJECT                     

Title                      

 

Adopt a Resolution Approving Addendum No. 1, Authorizing the City Manager to Award a Construction Contract to FBD Vanguard Construction, Inc., in the Amount of $801,832, Approving an Administrative Construction Contingency of $80,183; and Appropriating Additional Funds in the Amount of $141,000 for the South Hayward Safe Routes for Seniors Project, Project No. 05323                                                             

 

End
RECOMMENDATION

Recommendation

 

That City Council adopts the attached resolution (Attachment II):

1.                     Approving Addendum No. 1 consisting of clarifications and revisions to the project specifications; and

2.                     Authorizing the City Manager to award a construction contract to FBD Vanguard Construction, Inc., in the amount of $801,832 and approving an administrative construction contingency of $80,183; and

3.                     Appropriating additional funds in the amount of $141,000 from Measure BB (Pedestrian & Bicycle) Fund 213 to the South Hayward Safe Routes for Seniors Project No. 05323.

End

 

SUMMARY

 

The South Hayward Safe Routes for Seniors Project includes sidewalk and crossing improvements near senior-serving locations in South Hayward, including West Tennyson Road, Oliver Drive, and three locations around Weekes Park:

•                     Patrick Avenue and Roosevelt Avenue

•                     Patrick Avenue and Gomer Street/Tampa Avenue

•                     Midblock crosswalk at 27350 Tampa Avenue

 

Major improvements consist of sidewalk bulb-outs, median refuge islands, rectangular rapid flashing beacons (RRFBs), and a pedestrian signal that opens a closed crosswalk.

 

On October 14, 2026, the City received 12 bids. FBD Vanguard Construction, Inc., submitted the apparent low bid of $801,832. Staff recommends awarding the contract to FBD Vanguard Construction, Inc., in the amount of $801,832 and approving an administrative construction contingency amount of $80,183. Staff is also requesting City Council approval of Addendum No. 1, which was issued to provide bidder clarifications and revise Technical Specifications.

 

ATTACHMENTS