File #: CONS 25-162   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 4/22/2025 Final action:
Subject: Adopt a Resolution Awarding a Contract to DeSilva Gates Construction LLC, for the Fiscal Year 2024-2025 Pavement Improvement Project, Project No. 05338, in the Amount of $12,570,061 and Authorizing an Administrative Change Order Budget of $949,939
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      April 22, 2025

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Awarding a Contract to DeSilva Gates Construction LLC, for the Fiscal Year 2024-2025 Pavement Improvement Project, Project No. 05338, in the Amount of $12,570,061 and Authorizing an Administrative Change Order Budget of $949,939                                                             

 

End
RECOMMENDATION

Recommendation

 

That the City Council adopts a resolution (Attachment II) approving Addendum No. 1 consisting of revisions to the plans and specification for the FY25 Pavement Improvement Project (PIP) and awarding the construction contract for the project to DeSilva Gates Construction LLC, (DSG) in the amount of $12,570,061 and authorizing an administrative change order budget of $949,939 for a total not to-exceed contract amount of $13,520,000.

End

 

SUMMARY

 

The Fiscal Year 2024-2025 PIP calls for the rehabilitation of fifty-one (51) street segments and preventive maintenance of fourteen (14) street sections for a total of sixty-five (65) street segments (Attachment III).  The proposed improvements will repair failed pavement segments and improve street surfaces.

 

On March 25, 2025, the project received six (6) bids. Three of the six bids were under the Engineer’s Estimate of $12,940,000. , The low bid received is $12,570,061 which is $369,939 or 2.9% under the Engineer’s Estimate.

 

Staff recommends award of the contract to the responsible low bidder, DSG, in the amount of $12,570,061 and authorizing a potential administrative change order budget of $949,939 to be used at the discretion of the Director of Public Works for potential change order work.

 

The project budget of $14,500,000 is funded via the Gas Tax, Road Repair and Accountability Act (RRAA) (SB1), Measure BB, Vehicle Registration Fees, Street Impact Fee, and Street System Improvement funds.

 

There is no General Fund contribution to this project.

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Resolution