File #: CONS 24-607   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 11/19/2024 Final action:
Subject: Adopt a Resolution Authorizing the Interim City Manager to Amend the Professional Services Agreement with Dewberry Architects, Inc., by $338,000 for a Not-to-Exceed Amount of $868,000; and Appropriate Additional Funds in the Amount of $338,000 from Capital Projects (Governmental) - Fund 405 for the Hayward Police Department Locker Room and Communications Center Building, Project No. 07420
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      November 19, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the Interim City Manager to Amend the Professional Services Agreement  with Dewberry Architects, Inc., by $338,000 for a Not-to-Exceed Amount of $868,000; and Appropriate Additional Funds in the Amount of $338,000 from Capital Projects (Governmental) - Fund 405 for the Hayward Police Department Locker Room and Communications Center Building, Project No. 07420                                                             

 

End
RECOMMENDATION

Recommendation

 

That Council adopts a resolution (Attachment II) authorizing the City Manager to:

1.                     Amend the Professional Services Agreement (PSA) with Dewberry Architects, Inc., (Dewberry) for the architectural design services for the Hayward Police Department (HPD) Locker Room & Communications Center Building Project No. 07420 by $338,000 for a not-to-exceed amount of $868,000.

2.                     Appropriate additional funds in the amount of $338,000 from Capital Projects (Governmental) - Fund 405 for the HPD Locker Room & Communications Center Building Project No. 07420.

End

 

SUMMARY

 

On February 22, 2022, Council approved the PSA with Dewberry for design services associated with the HPD Locker Room Project in an amount not-to-exceed $416,000.

 

On March 19, 2024, Council approved an additional $114,000 to complete the construction documents for the project.

 

A new Communication Center for the HPD has been added to the project, modifying the original one-story design to a two-story design including the required addition of an elevator, thus increasing the effort by Dewberry.

 

Staff is requesting an amendment to the PSA with Dewberry in the amount of $338,000 for a not-to-exceed amount of $868,000 in order to complete the construction bid documents.  Staff is also requesting additional appropriation of $338,000 from Capital Projects (Fund 405) for the HPD Locker Room & Communications Center Building, Project No. 07420.

 

 

 

ATTACHMENTS

Attachment I    Staff Report

Attachment II   Resolution