Skip to main content
File #: CONS 24-262   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 5/21/2024 Final action:
Subject: Adopt Resolutions Authorizing the City Manager to Amend the Professional Services Agreements with (1) Kitchell CEM for Extended Construction Support Services by $90,000 for a Not-to-Exceed Amount of $3,028,000, and (2) with ABC Inspections, Inc., by $50,000 for a Not-to Exceed Amount of $1,080,000 for the Fire Station 6 and Fire Training Center Project (FS6/FTC), Project Nos. 07481 and 07482
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution Kitchell CEM, 3. Attachment III Resolution ABC Inspectors

DATE:      May 21, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt Resolutions Authorizing the City Manager to Amend the Professional Services Agreements with (1) Kitchell CEM for Extended Construction Support Services by $90,000 for a Not-to-Exceed Amount of $3,028,000, and (2) with ABC Inspections, Inc., by $50,000 for a Not-to Exceed Amount of $1,080,000 for the Fire Station 6 and Fire Training Center Project (FS6/FTC), Project Nos. 07481 and 07482                                                             

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolutions (Attachments II, III) authorizing the City Manager to:

1.                     Amend the Professional Services Agreement (PSA) with Kitchell CEM (Kitchell) for extended construction management services for the FS6/FTC project by $90,000 for a not-to-exceed (NTE) amount of $3,028,000;

2.                     Amend the PSA with ABC Inspections, Inc. (ABC) for extended construction support services for the FS6/FTC project by $50,000 for a NTE amount of $1,080,000.

End

 

SUMMARY

 

The Fire Station 6 and Fire Training Center (FS6/FTC) project commenced construction on August 17, 2020, and was anticipated to be completed in the Fall of 2022. While fire department personnel have moved into the new fire station and Las Positas Chabot College District students are using the facility, there are remaining outstanding construction items that need to be completed in order to close out the project. It is anticipated that these items will be completed by the end of July 2024.

 

Throughout the course of construction, construction management services provided by Kitchell and inspector of record services provided by ABC have been necessary to ensure that construction complies with project plans, specifications, and codes and regulations. Council adopted resolutions authorizing the City Manager to execute agreements with Kitchell for construction management and with ABC for inspector of record services prior to the commencement of construction. Due to the extended construction duration, the current  budget allocated for services by these firms will not be sufficient to close out the project. Staff is requesting amendments in the amounts of $90,000 with Kitchell and $50,000 with ABC which are necessary to complete the project.

 

ATTACHMENTS

Attachment I                       Staff Report

Attachment II                     Resolution Kitchell CEM

Resolution III                     Resolution ABC Inspections, Inc.