File #: CONS 24-230   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 5/7/2024 Final action:
Subject: Adopt a Resolution Approving Addendum No. 1, Rejecting the Bid Protest and Awarding a Construction Contract to Radius Earthwork, Inc., in the Amount of $4,529,499 for the Main Street Complete Street Project, Project No. 05283, and Appropriating Additional Funds in the Amount of $2,604,499
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Bid Results Summary, 4. Attachment IV Sposeto Bid Protest & Earthwork Response, 5. Attachment V Radius Earthwork Information After Bid Opening

DATE:      May 7, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Approving Addendum No. 1, Rejecting the Bid Protest and Awarding a Construction Contract to Radius Earthwork, Inc., in the Amount of $4,529,499 for the Main Street Complete Street Project, Project No. 05283, and Appropriating Additional Funds in the Amount of $2,604,499

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolution (Attachment II):

 

1.                     Approving Addendum No. 1 for providing responses to bidders’ questions for the Main Street Complete Street Project, and;

2.                     Rejecting the bid protest of Sposeto Engineering, and;

3.                     Awarding a construction contract for the project to Radius Earthwork, Inc., in the amount of $4,117,499, and authorizing an administrative change order budget of $412,000, for a total not to exceed contract amount of $4,529,499, and;

4.                     Transferring and appropriating additional funds in the amount of $2,604,499

End

 

SUMMARY

 

On December 5, 2023, Council adopted a resolution approving the plans and specifications for the construction of the Main Street Complete Street Project. The project was advertised on February 23, 2024 after receiving the authorization document (E-76) from Caltrans on February 22, 2024.

 

Seven bids were received for the Project on March 26, 2024. On March 29, 2024, a bid protest was received from the apparent second low bidder Sposeto Engineering. City staff reviewed all bid proposals and the bid protest.

 

Staff is requesting Council’s approval of Addendum No. 1 which provided clarifications to bidders’ questions. Additionally, staff is also requesting that Council rejects the bid protest from Sposeto Engineering, and awards the contract to the responsible low bidder, Radius Earthwork Inc., in the amount of $4,529,499.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                     Resolution

Attachment III                     Bid Results Summary

Attachment IV                     Sposeto Bid Protest and Radius Earthwork Response

Attachment V                     Radius Earthwork Information After Bid Opening