File #: LB 25-010   
Section: Legislative Business Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 4/1/2025 Final action:
Subject: 2025 WIFIA Loan: Adopt Resolution of the City Council Authorizing the Execution and Delivery of a WIFIA Loan Agreement with the United States Environmental Protection Agency and a Related Promissory Note in the Maximum Principal Amount of $244,139,000 (Excluding Capitalized Interest) to Finance Certain Capital Improvements to the Wastewater System, Including the Water Resource Recovery Facility Improvements, and Approving Related Agreements and Actions (Report from Director of Public Works Ameri)
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III WIFIA Loan Agreement, 4. Attachment IV Term Sheet

DATE:      April 1, 2025

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

2025 WIFIA Loan: Adopt Resolution of the City Council Authorizing the Execution and Delivery of a WIFIA Loan Agreement with the United States Environmental Protection Agency and a Related Promissory Note in the Maximum Principal Amount of $244,139,000 (Excluding Capitalized Interest) to Finance Certain Capital Improvements to the Wastewater System, Including the Water Resource Recovery Facility Improvements, and Approving Related Agreements and Actions (Report from Director of Public Works Ameri)                                                             

 

End
RECOMMENDATION

Recommendation

 

That City Council adopts a resolution (Attachment II) authorizing the execution and delivery of a WIFIA Loan Agreement in the maximum principal amount of $244,139,000 to finance capital improvements to the Wastewater System, including the Water Resources Recovery Facility (WRRF) Phase II Project (the “Project”), and approving related agreements and actions.

End

 

SUMMARY

 

The City of Hayward’s Department of Public Works & Utilities is pursuing a major capital improvement project to improve the WRRF, formerly known as the Water Pollution Control Facility,  (WRRF Phase II Improvement Project, the “Project”) to meet the nutrient reduction mandate for treated effluent identified in the 3rd Nutrients Watershed Permit adopted by the California Regional Water Quality Control Board (Control Board) in July 2024. The total cost of the Project is estimated at $498 million, including capital costs, contingencies, and financing costs.

 

As part of the funding strategy, the City intends to finance approximately 49% of the Project costs through the U.S. Environmental Protection Agency’s Water Infrastructure Finance and Innovation Act of 2014 (WIFIA) loan program (the “WIFIA Loan”). The WIFIA loan is expected to be approximately $244.139 million and is expected to provide funding for construction costs between September 2026 and September 2028. The remaining cost will be funded by publicly sold revenue bonds, a newly received grant from the Water Resources Development Act (WRDA), and sewer fund reserves.

 

Similar to the 2025 Bonds, the WIFIA Loan will be secured by net revenues (total revenues minus operation and maintenance costs) received by the City from its wastewater collection, pumping, transport, treatment, storage, and disposal system (Wastewater System).

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Resolution

Attachment III                     Loan Agreement 

Attachment IV                     Term Sheet