DATE:      May 6, 2025

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the City Manager to Appropriate Funds in the Amount of $50,000 from Transportation System Improvement - Fund 460 for the Traffic Signal Upgrade at Huntwood Avenue, Project No. 05737                                                             

 

End
RECOMMENDATION

Recommendation

 

That the City Council adopts a resolution (Attachment II) approving the City Manager to appropriate additional funds in the amount of $50,000 from Transportation System Improvement - Fund 460 for the Traffic Signal Upgrade at Huntwood Avenue, Project No. 05737.

End

 

SUMMARY

 

The City was awarded a Highway Safety Improvement Program (HSIP) grant in the amount of $774,900 toward the construction portion of the total project cost of $965,000, for the traffic signal modification at Huntwood/Industrial and Huntwood/Sandoval Intersection Project.  City Council awarded the construction contract to W. Bradley Electric, Inc., in the amount of $860,919. Final Construction is anticipated to be completed by May 2025. Due to necessary changes made during construction to complete the improvement of these intersections, more funding is needed to complete the project. Staff is recommending an additional appropriation of $50,000.

 

ATTACHMENTS

Attachment I                                          Staff Report