DATE:      April 26, 2022

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT                     

 

Title                      

Adopt a Resolution Approving the Project List for FY23 Road Repair and Accountability Act Funding for the FY23 Pavement Improvement Project    

                                                        

End
RECOMMENDATION

 

Recommendation

That the Council adopts a resolution (Attachment II) approving the project list for Road Repair and Accountability Act (RRAA) FY23 funding for the FY23 Pavement Improvement Project (PIP).

 

End

SUMMARY

 

A yearly application must be submitted to the California Transportation Commission (CTC) to continue receiving RRAA funding, which must include a resolution approving a project list of street segments or defined regions of the City for the estimated revenue. The RRAA revenue estimate for FY23 is $3,000,000 and the project list includes the Hayward neighborhoods within the limits of Hesperian Blvd, A Street, BART, Jackson Street, Union Pacific Railroad, and West Winton Ave, as shown on Attachment III.

 

ATTACHMENTS

Attachment I                         Staff Report

Attachment II                        Resolution

Attachment III                       Project Limits