DATE: August 9, 2022
TO: Mayor and City Council
FROM: Director of Maintenance Services
SUBJECT
Title
Adopt a Resolution Awarding a Contract to The Garland Company for the Hayward Police Department Roof Replacement - 300 W. Winton Ave CIP Project No. 07203, in an Amount Not-to-Exceed $1,160,865
End
RECOMMENDATION
Recommendation
That the Council adopts resolutions (Attachments II and III): 1) Authorizing the City Manager to negotiate and execute a contract, in a form approved by the City Attorney, with The Garland Company, in an amount not-to-exceed $1,160,865 for a complete roof replacement to Hayward Police Department Headquarters at 300 W. Winton Ave; 2) Authorizing the transfer and appropriation of $1,160,865 from the Workers' Compensation Fund to the General Fund Capital Fund; and 3) Authorizing the transfer of $5,902,372 from the Workers' Compensation Fund to the General Fund to reimburse for over-allocations from prior fiscal years.
End
SUMMARY
The Hayward Police Department Headquarters (HPD) building at 300 W. Winton Ave. was built in 1975. The Maintenance Services Facilities Division is tasked with all preventative maintenance and component replacement within this facility. Timely preventative maintenance and capital replacement schedules are vital to maximizing the useful life of a facility's overall infrastructure, building systems, and components. Since the facility originally opened, a combination of periodic repairs and a timely preventative maintenance schedule have allowed the original roof from 1975 to remain serviceable well beyond its expected 30-40-year life cycle. However, based on the current condition, the roof is now in need of replacement. Over the past 5 years, occurrences of rainwater leaking into staff work areas has become all too frequent. This roofing replacement project is part of Facilities' commitment to provide facilities for employees and the public that are serviceable and in a good state of ...
Click here for full text