File #: CONS 24-329   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 6/18/2024 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Award a Construction Contract to Spencon Construction for the FY24 Sidewalk Rehabilitation and Wheelchair Ramps Project No. 05324 in the Amount of $684,312 and Approving $115,688 in Administrative Construction Contingency
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III District Map, 4. Attachment IV Bid Results Summary

DATE:      June 18, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the City Manager to Award a Construction Contract to Spencon Construction for the FY24 Sidewalk Rehabilitation and Wheelchair Ramps Project No. 05324 in the Amount of $684,312 and Approving $115,688 in Administrative Construction Contingency                                                             

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the resolution (Attachment II) Authorizing the City Manager to award a construction contract to the low bidder Spencon Construction Inc., in the amount of $684,312 for the FY24 Sidewalk Rehabilitation and Wheelchair Ramps Project in Districts 4 and 5, Project No. 05324 and authorization to increase the Administrative Change Order (ACO) amount from $90,000 to $115,688.

End

 

SUMMARY

 

On May 21, 2024, the City received seven (5) bids for the project ranging from $684,312 to

$1,2184,155 (Attachment IV). Spencon Construction Inc. of San Ramon submitted the lowest bid of $684,312, which is 3.6% lower than the Engineer’s Estimate of $710,000. ASG Builders of Mountain View submitted the second lowest bid in the amount of $774,123 which is 9% higher than the Engineer’s estimate. Staff are recommending that a construction contract be awarded to Spencon in the amount of $684,321.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                      Resolution

Attachment III                      District Map

Attachment IV                      Bid Summary Results