File #: CONS 24-331   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 6/25/2024 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Amend the Professional Services Agreement with Carollo Engineers, Inc., to Increase the Contract Amount by $378,774 for a Not-to-Exceed Amount of $1,764,354 to Provide Additional Construction Support Services for the Water Resource Recovery Facility (WRRF) Switchgear Rehabilitation Project No. 07656, and Appropriating Additional Funds in the Amount of $135,154
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution
DATE: June 25, 2024

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title

Adopt a Resolution Authorizing the City Manager to Amend the Professional Services Agreement with Carollo Engineers, Inc., to Increase the Contract Amount by $378,774 for a Not-to-Exceed Amount of $1,764,354 to Provide Additional Construction Support Services for the Water Resource Recovery Facility (WRRF) Switchgear Rehabilitation Project No. 07656, and Appropriating Additional Funds in the Amount of $135,154

End
RECOMMENDATION
Recommendation

That Council adopts the attached resolution (Attachment II):

1. Authorizing the City Manager to amend the professional services agreement (PSA) with Carollo Engineers, Inc., (Carollo) to increase the contract amount by $378,774 for a not-to-exceed amount of $1,764,354 to provide additional construction support services for the Water Resource Recovery Facility (WRRF) Switchgear Rehabilitation Project No. 07656; and

2. Appropriating additional funds in the amount of $135,154 from the Sewer System Replacement Fund (Fund 611).

SUMMARY

The WPCF treats an annual average flow of approximately eleven million gallons per day (MGD) and meets current requirements to discharge treated effluent to the deep waters of the San Francisco Bay. Originally installed in 1982, the existing main switchgear (MSB) is a key component of the power distribution system at the WPCF. The MSB along with several related 480-volt motor control centers (MCCs) and 480-volt distribution panelboards have provided power and controls to vital plant facilities for over forty years and are in need of replacement for continued operational reliability of the WRRF.

On May 18, 20211, Council authorized entering into a PSA with Carollo to provide engineering, design, and construction support services for the Switchgear Rehabilitation Project in an amount not-to-exceed $1,108,835. On June 27, 20232, Council authorized amend...

Click here for full text