Subject: Adopt a Resolution Authorizing the City Manager to Execute an Amendment to the Contract with AEI Consultants to Increase the Not-to-Exceed Amount by $200,000, for a Total Not-to-Exceed Amount of $400,000 to Provide Environmental Services for the Stack Center Phase I and II Project
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      May 21, 2024

 

TO:           Mayor and City Council

 

FROM:     Assistant City Manager

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the City Manager to Execute an Amendment to the Contract with AEI Consultants to Increase the Not-to-Exceed Amount by $200,000, for a Total Not-to-Exceed Amount of $400,000 to Provide Environmental Services for the Stack Center Phase I and II Project

 

End
RECOMMENDATION

Recommendation

 

That Council adopts a resolution (Attachment II) authorizing the City Manager execute an amendment to the contract with AEI Consultants (AEI) to increase the not-to-exceed amount by $200,000, for a total not-to-exceed amount of $400,000 to provide environmental services for the Stack Center Phase I and II project.

End

 

SUMMARY

 

In 2021, the City selected AEI to conduct environmental studies for the Stack Center Phase I construction, including collecting soil sampling and investigations to ensure compliance with Alameda County Department of Environmental Health (ACDEH) requirements.  Staff will continue to work with AEI throughout the completion of Phase I of the project to address ACDEH conditional approval requirements. Staff is now recommending continuing receiving services from AEI consultants by increasing the not-to-exceed amount by $200,000 for a total amount not-to-exceed $400,000 to continue their environmental consulting services on Phase I and Phase II of the Stack Center project.

 

ATTACHMENTS

Attachment I                                           Staff Report