File #: WS 19-044   
Section: Work Session Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 7/9/2019 Final action:
Subject: Update on the South Hayward Youth and Family Center Project
Attachments: 1. Attachment I Staff Report, 2. Attachment II Draft Site Master Plan, 3. Attachment III Complete Streets Proposed Study Route

DATE:      July 9, 2019

 

TO:           Mayor and City Council

 

FROM:     Fire Chief

 

SUBJECT                     

 

Title                      

Update on the South Hayward Youth and Family Center Project             

                                                 

End
RECOMMENDATION

Recommendation

 

That Council accepts this report and provides comments.

End

 

SUMMARY

 

Since 2013, the City of Hayward, Alameda County (County), and Hayward Area Recreation and Parks District (HARD) have worked towards a shared vision of constructing and operating a new center at the corner of Tennyson and Ruus Roads. In 2015, the City, County, and HARD formed a Governance Group to guide the project. On February 5, 2019, the City Council authorized the City Manager to execute a contract with RossDrulisCusenbery, Inc. (RDC) to complete master planning and preliminary design for the site.

 

Since February, the multi-agency staff team has met with RDC regularly to conduct master planning for programming and site use. The staff team last reported to the Governance Group in May and will be updating the Group next at the end of this month. To prepare for that update, staff is seeking Council feedback on the following topics: 1) Proposed Project Goals, Branding, and Programming; 2) Parking Options; 3) Funding Strategies; 4) Tennyson Corridor Complete Streets Feasibility Study Route; and 5) HARD/City Land Swap and Use of the Matt Jimenez Community Center.

 

ATTACHMENTS

Attachment I                                           Staff Report

Attachment II                      Draft Site Master Plan

Attachment III                      Complete Streets Proposed Study Route