File #: CONS 23-604   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 11/14/2023 Final action:
Subject: Adopt Resolutions Authorizing the City Manager to Amend the Professional Services Agreements with (1) Kitchell CEM for Extended Construction Support Services by $98,000 for a Not-to-Exceed Amount of $2,631,000, (2) with RossDrulisCusenbery Architecture, Inc., by $107,000 for a Not-to Exceed Amount of $3,361,000; and (3) Transfer and Appropriate Additional Funds in an Amount of $2,030,000 for the Current Project Cost the Fire Station 6 and Fire Training Center Project, Project Nos. 07481 and 07482
Attachments: 1. Attachment I Staff Report, 2. Attachment II Kitchell Amendment Resolution, 3. Attachment III RDC Amendment Resolution, 4. Attachment IV Appropriation of Funds Resolution
DATE: November 14, 2023

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT

Title
Adopt Resolutions Authorizing the City Manager to Amend the Professional Services Agreements with (1) Kitchell CEM for Extended Construction Support Services by $98,000 for a Not-to-Exceed Amount of $2,631,000, (2) with RossDrulisCusenbery Architecture, Inc., by $107,000 for a Not-to Exceed Amount of $3,361,000; and (3) Transfer and Appropriate Additional Funds in an Amount of $2,030,000 for the Current Project Cost the Fire Station 6 and Fire Training Center Project, Project Nos. 07481 and 07482

EndRECOMMENDATION


Recommendation
That Council adopts the attached resolutions (Attachments II, III, IV) authorizing the City Manager to:
1. Amend the Professional Services Agreement (PSA) with Kitchell CEM (Kitchell) for extended construction management services for the Fire Station 6 and Fire Training Center (FS6/FTC) project by $98,000 for a not-to-exceed (NTE) amount of $2,631,000; and
2. Amend the PSA with RossDrulisCusenbery Architecture, Inc., (RDC) for extended construction support services for the FS6/FTC project by $107,000 for a NTE Amount of $3,361,000; and
3. Appropriate additional funds for the FS6/FTC project in the amount of $2,030,000 for the current project cost.

End
SUMMARY

The Fire Station 6 and Fire Training Center (FS6/FTC) project commenced construction on August 17, 2020, and was anticipated to be completed in the Fall of 2022. While fire department personnel have moved into the new fire station and Las Positas Chabot College District students are using the facility, there are remaining outstanding construction items that need to be completed in order to close out the project. It is anticipated that these items will be completed by the end of January 2024.

Throughout the course of construction, construction management services provided by Kitchell and construction support services provided by RD...

Click here for full text