DATE: January 17, 2023
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt a Resolution Awarding a Contract to JMB Construction for the Trash Capture Device Installation on Tennyson Road, Project No. 07746, in an Amount of $737,888 and a Contingency Budget of $72,112 for a Total Contract Not-to-Exceed Amount of $810,000
End
RECOMMENDATION
Recommendation
That the Council adopts a resolution (Attachment II) awarding the contract to JMB Construction for the Trash Capture Device Installation on Tennyson Road (Project), Project No. 07746, in the amount of $ 737,888 and a contingency budget of $72,112 for a total contract not-to-exceed (NTE) amount of $810,000.
End
SUMMARY
The Project will install two Continuous Deflective Separator (CDS) trash capture devices in the existing storm drainpipes in the I-880 Right-of-Way (ROW) near Tennyson Road to capture trash from the storm water system as part of the City’s trash reduction mandate from the San Francisco Regional Water Quality Control Board (Water Board). According to a cooperative implementation agreement between the City and Caltrans to install trash capture projects to achieve mutual trash reduction credit, the project will be funded by Caltrans. On October 25 2022, staff released a call for bids and received six (6) responses. Staff is requesting Council’s approval to award the construction contract to JMB Construction.
ATTACHMENTS
Attachment I Staff Report
Attachment II Resolution