DATE: September 20, 2016
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
I-880/92 Reliever Route: Phase 1 Project - Design Agreement and Construction Agreement Amendments
RECOMMENDATION
That Council adopts the attached resolutions (Attachments II and III):
1. Authorizing the City Manager to amend the Professional Services Agreement with Kimley-Horn and Associates, Inc. for an additional amount not-to-exceed $182,000 for construction support services; and
2. Authorizing the City Manager to increase the construction contingency in the contract with O.C. Jones and Sons, Inc. from $885,957 to $1,952,957 for a total construction contract amount not-to-exceed $13,002,000.
ATTACHMENTS
Attachment I Staff Report
Attachment II Resolution
Attachment III Resolution