DATE: December 1, 2026
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Corporation Yard Improvements: Needs Assessment Project Update (Report from Director of Public Works Ameri)
End
RECOMMENDATION
Recommendation
That the City Council receives and comments on this update regarding the Corporation Yard Needs Assessment Project.
End
SUMMARY
The City’s Corporation Yard was originally constructed in the 1960s, when the City’s population was about 80,000. The Corporation Yard supports essential City operations including Public Works and Utilities, Maintenance Services, Fleet Services, Animal Services, and Hayward Police Department (HPD) functions. The City population has grown since then to more than double. In addition, the existing facility has aging infrastructure, inadequate space and outdated systems, and no longer meets the City’s current or future operational needs.
On April 22, 2025, City Council authorized a Professional Services Agreement with Griffin Structures (Griffin) in an amount not-to-exceed $230,000 to conduct a comprehensive needs assessment and site planning effort for the Corporation Yard. The scope included evaluating existing conditions, determining current and future space requirements, developing conceptual site designs, and preparing preliminary project costs and construction phasing.
Since that time, Griffin has worked with City staff including the different departments and divisions operating from the Corporation Yard to evaluate existing facilities and operational needs. The assessment included questionnaires, site investigations, detailed staff interviews, a facility condition assessment and development of current and projected space needs over the next 10 to 20 years.
Based on this assessment, Griffin developed three conceptual alternatives, Concepts A, B, and C. Following evaluation with City staff, Concept B and Concept C were selected for further dev...
Click here for full text