Subject: Adopt a Resolution Authorizing the City Manager to Negotiate and Execute a Contract with Hi-Lite Airfield Services for Pavement Improvements of the Airport Hangar Improvement Project No. 06826 in a Not-To-Exceed Amount of $244,387.10, and Approving $24,438.71 in Administrative Construction Contingencies
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      August 18, 2026

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the City Manager to Negotiate and Execute a Contract with Hi-Lite Airfield Services for Pavement Improvements of the Airport Hangar Improvement Project No. 06826 in a Not-To-Exceed Amount of $244,387.10, and Approving $24,438.71 in Administrative Construction Contingencies                                                               

 

End
RECOMMENDATION

Recommendation

 

That the City Council adopts a resolution (Attachment II) authorizing the City Manager to negotiate and execute a Contract with Hi-Lite Airfield Services for the Airport Hangar Improvement Project No. 06826, in an amount not-to-exceed $244,387.10 and approving $24,438.71 in Administrative Construction Contingencies.

End

 

SUMMARY

 

The Airport Hangar Improvement Project No. 06826 will be used to repair and maintain T-Hangars located at the Hayward Executive Airport.  The project will include a seal coat, crack seal, and markings of approximately 265,482 square feet.

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Resolution