Subject: 21st Century Library and Community Learning Center and Heritage Plaza: Public Contract Code ยง 4107 Hearing Regarding Removal and Substitution of the Electrical Subcontractor, Collins Electrical Company, Inc (Report from Public Works Director Ameri and City Attorney Lawson) (Continued from July 16, 2019)
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:                     July 9, 2019

 

TO:                     Mayor and City Council

 

FROM:                     Director of Public Works

                     City Attorney

 

SUBJECT                     

 

21st Century Library and Community Learning Center and Heritage Plaza: Public Contract Code § 4107 Hearing Regarding Removal and Substitution of the Electrical Subcontractor, Collins Electrical Company, Inc.

 

RECOMMENDATION

 

That the Council, after conducting a hearing, considers and approves a resolution for the removal of Collins Electrical Company, Inc. as the electrical subcontractor on the 21st Century Library project and authorizes the City Manager to approve a substitute subcontractor to perform the electrical work pursuant to Public Contract Code § 4107.

 

SUMMARY

 

On July 2, 2019, the City transmitted a letter to T. B. Penick & Sons, Inc. (TBP) requesting that they remove Collins Electrical Company, Inc., (Collins) from the project and identify a responsible electrical contractor for submittal as a substitute. The request is based on disruptive actions and project delays attributed to Collins.  The City sent a notification to Collins regarding its request that TBP remove them as a subcontractor on this project. 

 

The terms of the construction contract for the library project require the contractor to immediately remove a subcontractor who fails to satisfactorily prosecute the work, upon request by the City.   The Public Contract Code requires a public hearing by the awarding authority whenever a subcontractor objects to being removed from a project and replaced with a substitute. 

 