DATE: December 1, 2026
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt a Resolution Authorizing the City Manager to Execute a Sole Source Agreement with Northeast-Western Energy Systems USA, LLC, in a Not-To-Exceed Amount of $157,223.87, Including 10% Contingency, for the Cogeneration System Maintenance Project, Project No. 07679
End
RECOMMENDATION
Recommendation
That the City Council adopts a resolution (Attachment II) authorizing the City Manager to execute a sole source agreement with Northeast-Western Energy Systems USA, LLC, (Energy Systems USA), in an amount not-to-exceed $157,223.87, including 10% contingency, for the Cogeneration System Maintenance Project.
End
SUMMARY
The City of Hayward’s Water Resource Recovery Facility (WRRF) treats an average of 11 million gallons per day (MGD) and complies with all current effluent discharge regulations.
The WRRF’s cogeneration system uses biogas produced in the facility’s anaerobic digesters to generate electricity and heat. Together with the WRRF’s 1.6 Megawatt (MW) solar facility, the cogeneration system provides more power than the WRRF needs, and excess energy is exported to the grid to offset energy use at other City facilities.
The engine manufacturer’s maintenance schedule requires the cylinder heads to be replaced after 30,000 hours of service. Replacing the cylinder heads is necessary to prevent engine failure, avoid extended outage of the cogeneration system, and maintain compliance with the facility’s air permit.
Energy Systems USA, who is the sole source vendor for Jenbacher Cogeneration engines on the West Coast, will perform services for the cogeneration system. Energy Systems USA submitted a quote for this work in October 2026 in the amount of $142,930.79. Staff recommends an additional 10% contingency for a total contract award of $157,223.87.