DATE: June 27, 2023
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt Resolutions Authorizing the City Manager to (1) Award a Construction Contract to W. Bradley Electric in the Amount of $280,833 and Approving $42,125 in Administrative Construction Contingency; and (2) Appropriate $137,125 from the Measure BB Local Transportation (Fund 212) to the Safe Routes to School - Cesar Chavez Middle School, Project No. 05319
End
RECOMMENDATION
Recommendation
That Council adopts the resolutions (Attachments II and III) authorizing the City Manager to:
1. Award a Construction Contract to W. Bradley Electric, for the Safe Routes to School (SR2S) - Cesar Chavez Middle School (CCMS) Project No. 05319, in the amount of $280,833 and approve $42,125 in Administrative Construction Contingency; and
2. Appropriate $137,125 from the Measure BB Local Transportation (Fund 212) to the SR2S - CCMS Project No. 05319
End
SUMMARY
On January 24, 2023, Council approved the plans, specifications and call for bids for the SR2S Project. The SR2S Program, funded by Alameda County Transportation Commission (ACTC), supports safe access and mobility to and from schools by funding sustainable transportation improvement for pedestrians, cyclists, and transit riders. In FY22, the City was successful in obtaining the SR2S Mini-Grant to fund improvements for CCMS, including installation of paint and post curb extensions, yellow high-visibility crosswalks, pedestrian push buttons, two rapid flashing beacon systems, and signage among other enhancements. One bid was received for this project. After reviewing the bid proposal, staff deemed the bid unresponsive. Council rejected the sole unresponsive bidder and approved the revised plans and specifications on April 25, 2023 .
On May 16, 2023, two (2) bids were received for the SR2S project. Staff recommends that Council award the contract to the responsible low bidder, W....