DATE: October 28, 2020
TO: Council Infrastructure Committee
FROM: Director of Public Works
SUBJECT
Title
Update on the Hayward 21st Century Library and Community Learning Center Improvement Project
EndRECOMMENDATION
Recommendation
That the Council Infrastructure Committee reviews this report and comments on the progress of the construction of the Library building and the Library Plaza Project.
End
SUMMARY
The 21st Century Library and Community Learning Center and Heritage Plaza project was approved by Council in May 2015. The project includes a new Main Library, deconstruction of the old Main Library, and construction of the Heritage Plaza. The Library building and related facilities were commissioned in September 2019 and are nearly complete. The Library Plaza is under construction and expected to be completed by late December.
ATTACHMENTS
Attachment I Staff Report