DATE:      December 5, 2017

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Authorization for the City Manager to Execute a Professional Services Agreement for Bicycle and Pedestrian Master Plan Update 2017                                                  

 

End
RECOMMENDATION

Recommendation

 

That the Council:

(1)                     adopts a resolution authorizing the City Manager to execute a Professional Services Agreement with Kittelson & Associates, Inc. in an amount not-to-exceed $300,000 to complete the 2017 Bicycle and Pedestrian Master Plan Update; and

(2)                     appropriates an additional $40,000 to this project from Measure B Fund 216.  

End

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Resolution

Attachment III                     Scope of Work