File #: CONS 20-616   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 12/8/2020 Final action:
Subject: Adopt a Resolution Approving an Amendment to Professional Services Agreement with Kimley-Horn and Associates, Inc., for the Hayward Boulevard Safety Improvements Feasibility Study in the Amount of $44,990, Increasing the Total Contract to an Amount Not to Exceed $178,825
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      December 8, 2020

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT

 

Adopt a Resolution Approving an Amendment to Professional Services Agreement with Kimley-Horn and Associates, Inc., for the Hayward Boulevard Safety Improvements Feasibility Study in the Amount of $44,990, Increasing the Total Contract to an Amount Not-to- Exceed $178,825


RECOMMENDATION

 

That Council adopts a resolution (Attachment II) authorizing the City Manager to execute Amendment No. 1 to the Professional Services Agreement (PSA) with Kimley-Horn and Associates, Inc. (KHA), in the amount of $44,990, increasing the total contract to an amount not-to-exceed $178,825 for additional design and public outreach related services, and appropriate additional funds from the Local Transportation Fund (Fund 212).

 

SUMMARY

 

An amendment to the existing agreement with KHA is needed for increased design and public outreach services. The amendment will increase the contract by $44,990 for a total amount not to exceed $178,825. The proposed contract amendment would allow KHA to provide additional design services for the development of two more conceptual alternatives, as well as to provide one additional round of public outreach.

 

ATTACHMENTS

Attachment I                       Staff Report

Attachment II                      Resolution