DATE:      October 28, 2020

 

TO:           Council Infrastructure Committee

 

FROM:     Director of Public Works                     

 

SUBJECT                     

Title                      

Main Street Complete Streets Update                                                             

End
RECOMMENDATION

Recommendation

That the Council Infrastructure Committee (CIC) reviews the updated cost estimate, potential scope and cost reduction options, and provides direction to move forward with final design for the Main Street Complete Street project.

End

SUMMARY

 

Staff has updated the cost to support design, construction, inspection, and construction management for the development of Concept 1 of the Main Street complete streets project. The current cost is approximately $5.1 million ($4.4 million construction cost) and includes a 5% contingency.  The grant that funds the project provides approximately $1.7 million.  Thus, there is a budget shortfall of approximately $3.4 million.

 

The Safe Routes for Seniors (SR4S) project is currently contemplating improving the intersections of A Street and Main Street, and C Street and Main Street, among other intersections in the Downtown.  Staff is proposing to construct these two intersections as part of the Main Street Project, with funding, currently estimated at $1M, paid for by the SR4S project. This will reduce the budget shortfall to $2.2M. Staff recommends limiting the scope of the project as outlined in the report to further reduce the cost.

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Main St Concept 1

Attachment III                     Original Grant Application Estimate 2016

Attachment IV                                          Update Cost Estimate and Alternative