File #: CONS 24-593   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 11/19/2024 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Amend the Contract with EBA Engineering by $60,000 for the Removal of Underground Fuel Storage Tanks for a Not-to Exceed Amount of $222,343 for the Mission Boulevard Corridor Improvements Phase 3 Project, Project No. 05287
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      November 19, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Authorizing the City Manager to Amend the Contract with EBA Engineering by $60,000 for the Removal of Underground Fuel Storage Tanks for a Not-to Exceed Amount of $222,343 for the Mission Boulevard Corridor Improvements Phase 3 Project, Project No. 05287                                                     

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolution (Attachment II) authorizing the City Manager to amend the Contract with EBA Engineering (EBA) for additional services to remove an additional three underground fuel storage tanks for the Mission Boulevard Corridor Improvements Phase 3 project by $60,000 for a not-to-exceed amount of $222,343.

End

 

SUMMARY

 

Construction of the Mission Boulevard Corridor Improvements Phase 3 project from A Street to Rose Street started on July 10, 2023. After the start of construction, several unforeseen issues were encountered that have extended the estimated construction completion date to Summer of 2025.

 

One of the issues encountered during construction was an unanticipated existing underground fuel storage tank (UST). The UST encountered was removed by EBA through a purchase order. On September 17, 2024, Council authorized the City Manager to amend EBA’s contract to remove three additional USTs when these were discovered at a different location. Since then, another UST has been discovered and needs to be removed. The cost to remove this additional UST exceeds the previous amended amount.

 

Staff recommends that Council authorizes the City Manager to amend the contract with EBA to increase the contract amount by $60,000, with a total NTE amount of $222,343.

 

ATTACHMENTS

Attachment I     Staff Report

Attachment II   Resolution