DATE: May 21, 2024
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt Resolutions Authorizing the City Manager to Amend the Professional Services Agreements with (1) Kitchell CEM for Extended Construction Support Services by $90,000 for a Not-to-Exceed Amount of $3,028,000, and (2) with ABC Inspections, Inc., by $50,000 for a Not-to Exceed Amount of $1,080,000 for the Fire Station 6 and Fire Training Center Project (FS6/FTC), Project Nos. 07481 and 07482
End
RECOMMENDATION
Recommendation
That Council adopts the attached resolutions (Attachments II, III) authorizing the City Manager to:
1. Amend the Professional Services Agreement (PSA) with Kitchell CEM (Kitchell) for extended construction management services for the FS6/FTC project by $90,000 for a not-to-exceed (NTE) amount of $3,028,000;
2. Amend the PSA with ABC Inspections, Inc. (ABC) for extended construction support services for the FS6/FTC project by $50,000 for a NTE amount of $1,080,000.
End
SUMMARY
The Fire Station 6 and Fire Training Center (FS6/FTC) project commenced construction on August 17, 2020, and was anticipated to be completed in the Fall of 2022. While fire department personnel have moved into the new fire station and Las Positas Chabot College District students are using the facility, there are remaining outstanding construction items that need to be completed in order to close out the project. It is anticipated that these items will be completed by the end of July 2024.
Throughout the course of construction, construction management services provided by Kitchell and inspector of record services provided by ABC have been necessary to ensure that construction complies with project plans, specifications, and codes and regulations. Council adopted resolutions authorizing the City Manager to execute agreements with Kitchell for construction management and with ABC for inspector of record services prior to the co...
Click here for full text