DATE: March 18, 2025
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt a Resolution Approving Addendums No. 1, No. 2, No. 3 and No. 4, and Authorizing the City Manager to 1) Award a Construction Contract to Rodan Builders, Inc., for a Not-to-Exceed Amount of $43,967,000, 2) Amend the Existing Professional Service Agreements with Carollo Engineers and Brown, and Caldwell for the Water Resource Recovery Facility's (WRRF) New Administration Building and Laboratory Project, Project No. 07786 and WRRF Phase II Improvement Project No. 07760
End
RECOMMENDATION
Recommendation
That City Council adopts the attached resolution (Attachment II):
1. Approving Addendums No. 1, No. 2, No. 3, and No. 4, which were issued to make minor revisions to the plans and specifications and to answer bidder clarification questions for the Water Resource Recovery Facility's (WRRF) New Administration Building and Laboratory Project, Project No. 07786;
2. Authorizing the City Manager to Award a Construction Contract to Rodan Builders, Inc., (Rodan Builders) for the WRRF New Administration Building and Laboratory Project No. 07786, in an Amount Not-to-Exceed $43,967,000;
3. Authorizing the City Manager to Amend the Professional Services Agreement (PSA) with Brown and Caldwell, California Corporation (Brown and Caldwell), to include engineering services during construction for the WRRF New Administration Building and Laboratory Project, as well as bid period services for the WRRF Improvements - Phase II, increasing the contract amount by $1,422,748 to a not-to-exceed limit of $18,095,575; and
4. Authorizing the City Manager to Amend the PSA with Carollo Engineers, Inc. (Carollo), to include construction management services for the WRRF New Administration Building and Laboratory Project increasing the contract amount by $3,428,409 to a not to exceed limit of $4,378,034.
End
SUMMARY
The WRRF treats an annual a...