File #: CONS 24-134   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 3/26/2024 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Execute the Project Initiation Document for the SR-92/Whitesell Interchange Project, Project No. 05334
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Draft PID Document
DATE: March 26, 2024

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT

Title
Adopt a Resolution Authorizing the City Manager to Execute the Project Initiation Document for the SR-92/Whitesell Interchange Project, Project No. 05334

End
RECOMMENDATION

Recommendation
That the Council adopts a resolution (Attachment II) authorizing the City Manager to sign the final Project Initiation Document (PID) for the SR-92/Whitesell Interchange Project on behalf of the City.

End
SUMMARY

The State Route-92 (SR-92)/Clawiter Road interchange is the last interchange on SR-92 just east of the San Mateo-Hayward Bridge crossing at the San Francisco Bay and approximately two miles west of the SR-92/Interstate-880 (I-880) interchange. The Project is located in the western portion of the City in an area that is generally built out and characterized primarily by industrial land uses.

The proposed SR-92/Whitesell Interchange Project would further enhance the local reliever route between SR-92 and I-880, and significantly improve access to and from the City's industrial complexes, manufacturing sites, and office parks north and south of SR-92 and west of I-880. It would also improve bike and pedestrian connectivity across the interchange and operations of the interchange to further relieve congestion on SR-92, I-880 and major arterials in the area.

The purpose of the PID phase is to define the general scope of the environmental studies and engineering reports that will be necessary to comply with the California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA) in the next phase of development, Project Approval and Environmental Document (PA&ED). The preliminary alternatives developed in the PID will be further refined during the PA&ED phase through consultation with stakeholders and the public as required by CEQA and NEPA.

The City, in collaboration with Caltrans, is preparing the pro...