File #: CONS 22-017   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 1/18/2022 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Execute an Amendment to the Professional Services Agreement for Materials Testing and Special Inspection Services with Consolidated Engineering Laboratories for the Fire Station 6 and Fire Training Center Project by $450,000 for a Not-to-Exceed Amount of $1,125,000
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      January 18, 2022

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT                     

 

Title                      

Adopt a Resolution Authorizing the City Manager to Execute an Amendment to the Professional Services Agreement for Materials Testing and Special Inspection Services with Consolidated Engineering Laboratories for the Fire Station 6 and Fire Training Center Project by $450,000 for a Not-to-Exceed Amount of $1,125,000             

                                               

End
RECOMMENDATION

 

Recommendation

That the Council adopts a resolution (Attachment II) authorizing the City Manager to execute an amendment to the professional services agreement (PSA) for materials testing and special inspection services with Consolidated Engineering Laboratories (CEL) in an amount not-to-exceed $450,000, thereby increasing the total contract amount to $1,125,000 for the Fire Station 6 (FS6) and Fire Training Center Project (FTC).

 

End

SUMMARY

 

The FS6 and FTC Project commenced construction on August 17, 2020, and is anticipated to be completed in Fall 2022. Construction requires materials testing and special inspection services to ensure that the materials and construction comply with project plans, specifications, and codes. Furthermore, buildings owned by the Chabot-Las Positas Community College District (District) require testing and inspections pertaining to specific regulations of the Division of the State Architect (DSA). On May 25, 2021, Council adopted the resolution authorizing the City Manager to execute the first amendment to the PSA with CEL in the amount of $325,000. The amended amount is nearly exhausted. A second amendment in the amount of $450,000 is necessary to complete the project.

 

ATTACHMENTS

Attachment I    Staff Report

Attachment II   Resolution