Subject: Adopt a Resolution Awarding a Construction Contract to QA Constructors, Inc. for the Alves Street and Leighton Street Drainage Improvements, Project No. 07794, in the Amount of $132,250 and Approving an Administrative Change Order Budget of $32,750.
Attachments: 1. Attachment l Staff Report, 2. Attachment II Resolution

DATE:      May 21, 2024

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Awarding a Construction Contract to QA Constructors, Inc. for the Alves Street and Leighton Street Drainage Improvements, Project No. 07794, in the Amount of $132,250 and Approving an Administrative Change Order Budget of $32,750.                                                             

 

End
RECOMMENDATION

Recommendation

 

That the Council adopts a resolution (Attachment II) Awarding a construction contract for the Alves Street and Leighton Street Drainage Improvements Project to QA Constructors, Inc., in the amount of $132,250, and authorizing an administrative change order budget of $32,750 for a total not-to-exceed contract amount of $165,000.

End

 

SUMMARY

 

This Project proposes drainage improvements by constructing a valley gutter at the intersection of Alves Street and Leighton Street. The Project will also include street pavement grading at the intersection to allow for more optimal drainage from the residential houses to the valley gutter.

 

On April 23, 2024, the project received five (5) bids. Staff recommends that Council award the contract to the responsible low bidder, QA Constructors, Inc., of San Francisco, CA in the amount of $132,250 and authorizing an administrative change order budget of $32,750.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                     Resolution