Subject: Adopt a Resolution Approving Addendum Nos. 1,2,3 and 4, Rejecting the Bid from CWS Construction Group, Inc. and Awarding a Construction Contract to Rodan Builders, Inc., for The Stack Center - Phase I Project, Project No. 06960, in the Amount of $8,699,000 and Authorizing an Administrative Change Order Budget of $871,000
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Location Map
DATE: December 12, 2023

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title

Adopt a Resolution Approving Addendum Nos. 1,2,3 and 4, Rejecting the Bid from CWS Construction Group, Inc. and Awarding a Construction Contract to Rodan Builders, Inc., for The Stack Center - Phase I Project, Project No. 06960, in the Amount of $8,699,000 and Authorizing an Administrative Change Order Budget of $871,000

End
RECOMMENDATION
Recommendation

That the Council adopts a resolution (Attachment II):
(1) Approving Addendum Nos. 1,2,3, & 4 consisting of revisions to the plans and specification for The Stack Center - Phase I Project, and;
(2) Rejecting the bid from CWS Construction Group, Inc., and;
(3) Awarding a construction contract for the project to Rodan Builders, Inc., in the amount of $8,699,000, and authorizing an administrative change order budget of $871,000, for a total not to-exceed contract amount of $9,570,000.

End
SUMMARY

Community members and elected officials have long held the dream of building a new South Hayward Youth and Family Center at the corner of Tennyson and Ruus Roads, referred to as The Stack Center. For the past seven years, the City and its partners have worked to raise funds and define the vision for this Center.

On November 30, 2023, the project received four (4) bids. The lowest bidder, CWS Construction Group, Inc., did not meet the qualifications/experience requirements of the bid. Staff recommends that Council reject the lowest bid and award of the contract to the second lowest responsible bidder, Rodan Builders, Inc., of Hayward in the amount of $8,699,000 and authorizing an administrative change order budget of $871,000. At $8,699,000, the bid is $301,000 or 3.3% under the engineer's estimate of $9,000,000.

The attached resolution approves the award of contract for Phase I construction, which consists of rehabilitating the existing Matt Jimenez Community Center (MJC...

Click here for full text