Skip to main content
File #: CONS 24-519   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 10/8/2024 Final action:
Subject: Adopt a Resolution Authorizing the City Manager to Execute Amendment No. 1 to Increase the Professional Services Agreements with Kitchell CEM for Extended Construction Support Services by $2,138,812 for a Not-to-Exceed Amount of $2,658,812 for The Stack Center Phase I and Phase II Projects, Project No. 06960
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Project Map
DATE: October 8, 2024

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title

Adopt a Resolution Authorizing the City Manager to Execute Amendment No. 1 to Increase the Professional Services Agreements with Kitchell CEM for Extended Construction Support Services by $2,138,812 for a Not-to-Exceed Amount of $2,658,812 for The Stack Center Phase I and Phase II Projects, Project No. 06960

End
RECOMMENDATION
Recommendation

That Council adopts the attached resolution (Attachment II) to Amend the Professional Services Agreement (PSA) not-to-exceed amount of $520,000 with Kitchell CEM (Kitchell) for extended construction management services in the amount of $136,675 (Attachment III) for The Stack Center Phase I project to approve an additional $2,002,137 (Attachment IV) for The Stack Center Phase II project, for a total of $2,138,812, for a Not-to Exceed Amount of $2,658,812.

End

SUMMARY

Under the existing PSA, Kitchell provides construction management services for The Stack Center Phase I Project which is currently under construction for a not-to-exceed amount of $520,000.

The Stack Center Phase I project consists of rehabilitating the existing Matt Jimenez Community Center (MJCC) to house a preschool and daycare facility and improving external elements surrounding the MJCC (Attachment V). The project commenced construction on February 13, 2024, and is scheduled for completion in November 2024. Kidango's affordable childcare programming is anticipated to move into the MJCC in Spring 2025.

Originally, construction of the Phase I project was to begin in November 2022. However, due to delays in obtaining an environmental site clearance from Alameda County Department of Environmental Health (ACDEH) and obtaining City permits, construction was delayed and began over a year later in February 2024. During this time, Kitchell expended unexpected but needed support services between Nove...

Click here for full text