Subject: I-880/SR-92 Reliever Route: Phase 1 Project - Amendment to Construction Agreement with O.C. Jones and Sons, Inc. (O.C. Jones)
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      July 10, 2018

 

TO:           Mayor and City Council

 

FROM:     Interim Director of Public Works

 

SUBJECT                     

Title                      

 

I-880/SR-92 Reliever Route: Phase 1 Project - Amendment to Construction Agreement with O.C. Jones and Sons, Inc. (O.C. Jones)                                                             

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolution:

 

1.                     Increasing the total project cost for the Interstate 880 (I-880)/ State Route 92 (SR-92) Reliever Route Phase I project by an additional $300,000; and

2.                     Increasing the construction contingency in the contract with O.C. Jones from $2,350,957 to $2,450,957 for a total construction contract amount not-to-exceed $13,500,000.

End

 

SUMMARY

 

O.C. Jones is the construction contractor for the I-880/SR-92 Reliever Route Phase I project. Construction is complete, and all change order requests and claims have been negotiated and resolved. This amendment increases the authorized funding by $300,000, and the construction contingency by $100,000. The additional cost was included in the Adopted FY19 Capital Improvement Program (CIP).

 