File #: CONS 17-432   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 7/18/2017 Final action:
Subject: Cast Iron Water Pipeline Replacement Project: Approval of Additional Funds to Pay Contract's Retention and Close the Project RECOMMENDATION
Attachments: 1. Attachment I Staff Report, 2. Attachment II Draft Resolution, 3. Attachment III Project Location Map, 4. Attachment IV Statement of Final Quantities

DATE:      July 18, 2017

 

TO:           Mayor and City Council

 

FROM:     Director of Utilities and Environmental Services

 

SUBJECT

 

Title                      

Cast Iron Water Pipeline Replacement Project: Approval of Additional Funds to Pay Contract’s Retention and Close the Project

RECOMMENDATION

 

Recommendation

That Council adopts the attached resolution increasing the construction contract by $46,327 to cover the unanticipated cost of additional paving required to complete the water pipeline replacement project.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                     Resolution

Attachment III                      Project Location Map

Attachment IV                     Statement of Final Quantities