DATE: July 18, 2017
TO: Mayor and City Council
FROM: Director of Utilities and Environmental Services
SUBJECT
Title
Cast Iron Water Pipeline Replacement Project: Approval of Additional Funds to Pay Contract’s Retention and Close the Project
RECOMMENDATION
Recommendation
That Council adopts the attached resolution increasing the construction contract by $46,327 to cover the unanticipated cost of additional paving required to complete the water pipeline replacement project.
ATTACHMENTS
Attachment I Staff Report
Attachment II Resolution
Attachment III Project Location Map
Attachment IV Statement of Final Quantities