DATE: June 19, 2018
TO: Mayor and City Council
FROM: Director of Utilities & Environmental Services
SUBJECT
Title
Water Pollution Control Facility Final Clarifier and Gravity Belt Thickener Sludge Blending Tank Rehabilitation Project: Approval of Addendum No. 1 and Award of Construction Contract, and Appropriation of Funds
End
RECOMMENDATION
Recommendation
That Council adopts the attached resolutions approving Addendum No. 1 which provided minor revisions to the Plans and Specifications, awarding the contract to GSE Construction Company, Inc., in the amount of $2,137,100, and appropriating additional funds in the amount of $68,100.
End
SUMMARY
The Water Pollution Control Facility (WPCF) Final Clarifier and Gravity Belt Thickener (GBT) Sludge Blending Tank Rehabilitation Project (Project) consists of the following four project elements:
1. Final Clarifier Structure Repair and Mechanism Recoating
2. GBT Sludge Blending Tank Structure Repair
3. Primary Clarifier Effluent Box Capacity Increase
4. Drying Bed Filtrate Pipeline By-Pass
These improvements enable the WPCF to continue operating efficiently and reliably. Three (3) bids were received. Staff is requesting Council’s approval of Addendum No. 1 and award of the construction contract to the lowest bidder GSE Construction Company, Inc., at $2,137,100.
ATTACHMENTS
Attachment I Staff Report
Attachment II Draft Resolution
Attachment III Appropriation Resolution