DATE:      July 17, 2018

 

TO:           Mayor and City Council

 

FROM:     Director of Utilities & Environmental Services

 

SUBJECT                     

Title                      

 

Recycled Water Storage and Distribution System Project: Authorization to Execute an Amendment to Professional Services for Recycled Water Customer Retrofit Conversions to Increase the Contracted Amount for Additional Services                                                              

 

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolution authorizing the City Manager to amend the professional services agreement with HydroScience Engineers, Inc., to increase the contract amount by $118,000, to a not to exceed amount of $978,000, to provide additional recycled water support services.

End

 

SUMMARY

 

The City is implementing the Recycled Water Storage and Distribution System Project (Recycled Water Project), which would provide a locally sustainable and drought-proof supply of recycled water to customers for irrigation and industrial uses. The Recycled Water Project includes the permitting, design, and construction of irrigation system retrofits necessary to convert customers from the City’s potable drinking water system to the new recycled water system. This specialized work requires extensive knowledge and experience with recycled water regulations and customer irrigation systems. On March 20, 2017, the City and HydroScience, Inc. (HydroScience) entered into a professional services agreement (PSA) for HydroScience to provide engineering, design, and construction support services to retrofit customer sites to use recycled water. Staff is requesting Council approval to increase the contract amount with HydroScience by $118,000, to a not to exceed amount of $978,000, to provide additional recycled water support services.

 