DATE: October 24, 2018
TO: Council Infrastructure Committee
FROM: Interim Director of Public Works
SUBJECT
Title
Fire Station 6 and Fire Training Center Design- Update
EndRECOMMENDATION
Recommendation
That the Committee comments on the design for the Fire Station 6 and Fire Training Center Project.
End
SUMMARY
The design of Fire Station 6 and the Fire Training Center includes a full build out training center resulting from the partnership with the Chabot-Las Positas Community College District. The project is currently in the design phase pending several review requirements. Staff anticipates that the design will be completed in early 2019, with construction anticipated to start in the Fall of 2019.
ATTACHMENTS
Attachment I Staff Report