File #: PH 18-085   
Section: Public Hearing Status: Agenda Ready
Meeting Body: Planning Commission
Agenda Date: 11/8/2018 Final action:
Subject: Appeal of Denial of a Proposed Temporary Concrete Recycling Facility at 24701 Clawiter Road (APN: 439-0020-002-03) Kimberly Douglas for Bay Area Concrete Recycling, LLC. (Applicant)/S & A Investment Holdings (Owner) Requiring an Administrative Use Permit Application 201801996. (Continued from October 11, 2018)
Attachments: 1. Attachment I - Staff Report, 2. Attachment II - Findings for Denial, 3. Attachment III - Appeal Narrative, 4. Attachment IV - Chronology, 5. Attachment V - Plans, 6. Attachment VI - Public Comments, 7. Attachment VII - Notice of Violation, 8. Attachment VIII - Documentation Businesses at Clawiter October 2018

DATE:      November 8, 2018

 

TO:           Planning Commission

 

FROM:     Planning Manager

 

SUBJECT                     

Title                      

 

Appeal of Denial of a Proposed Temporary Concrete Recycling Facility at 24701 Clawiter Road (APN: 439-0020-002-03) Kimberly Douglas for Bay Area Concrete Recycling, LLC. (Applicant)/S & A Investment Holdings (Owner) Requiring an Administrative Use Permit Application 201801996. (Continued from October 11, 2018)                                                             

 

End
RECOMMENDATION

Recommendation

 

That the Planning Commission deny the appeal and uphold staff’s decision on denial of a Temporary Use Permit to continue the operation of an outdoor concrete recycling facility at the project site until such time that they receive approval of another Administrative Use Permit to operate a permanent concrete recycling facility at another location on Depot Road.

End

 

SUMMARY

 

Bay Area Concrete Recycling (BACR) is requesting an Administrative Use Permit to temporarily continue the operation of an outdoor concrete recycling facility at the project site until such time that they receive approval of another Administrative Use Permit to operate a permanent concrete recycling facility at another location on Depot Road.

 

ATTACHMENTS

Attachment I                                           Staff Report

Attachment II                                          Findings for Denial

Attachment III                      Appeal Narrative

Attachment IV                      Chronology

Attachment V                                          Plans

Attachment VI                      Public Comments

Attachment VII                      Notice of Violation

Attachment VIII                      Documentation - Businesses at Clawiter - October 2018