File #: CONS 18-743   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 11/13/2018 Final action:
Subject: Abatement and Deconstruction for Route 238 Bypass Property Project: Award of Construction Contract to Asbestos Management Group of CA, Inc.
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE:      November 13, 2018

 

TO:           Mayor and City Council

 

FROM:     Interim Director of Public Works

 

SUBJECT                     

 

Title

Abatement and Deconstruction for Route 238 Bypass Property Project: Award of Construction Contract to Asbestos Management Group of CA, Inc.                 

                                           

End
RECOMMENDATION

Recommendation

 

That Council adopts the attached resolution (Attachment II):

 

1.                     Awarding the contract to Asbestos Management Group of CA, Inc.  in the amount of $906,250 and authorizing the expenditure of up to $1,405,000 for the total project, including contingencies;

 

2.                     Authorizing the City Manager to Approve Plans and Specifications and Call for Bids for future phases of Hazardous Material Testing Reports for the Route 238 Bypass Property Project; and

 

3.                     Authorizing appropriation of $1,405,000 from Fund 411 - Property Development Fund Balance to Fund 411-238 Property Development Program 6710.

End

 

SUMMARY

 

Several buildings recently acquired by the City from the California Department of

Transportation (Caltrans) as part of the Route 238 Bypass Property project (Route 238) require hazardous materials testing and clean-up prior to deconstruction. EnviroNova, LLC., a hazardous materials and environmental consulting firm, provided hazardous material surveying, testing, and abatement plan reports for ten (10) properties acquired from Caltrans and one (1) additional City-owned downtown property in Phase 1 of the deconstruction project. The City continues to work with tenants who signed leases with Caltrans to find new housing and to vacate the remaining properties. Because these homes were recently vacated, staff added eight (8) more properties to the Phase 1 scope of work and expects reports for these added properties to be available during November 2018. Staff prepared construction contract documents using the available reports, issued a call for bids and now recommends Asbestos Management Group of CA, Inc., as the qualified selected contractor to perform the clean-up and deconstruction of Phase 1 parcels.  

 

The Request for Proposals dated April 16, 2018, identified fifty-three parcels to be included for deconstruction and abatement. Staff continues to work with the consultant to prepare the Plans and Specifications for the remaining parcels. To expedite future deconstruction and abatement, staff requests Council’s authorization for the City Manager to approve Plans and Specifications, once available, and call for bids for future phases of Route 238.

 