File #: CONS 19-081   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 2/19/2019 Final action:
Subject: New Garin Reservoir and Pump Station Improvements: Authorization for the City Manager to Amend Professional Services Agreement for Additional Engineering Services During Construction
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      February 19, 2019

 

TO:           Mayor and City Council

 

FROM:     Director of Utilities & Environmental Services

 

SUBJECT                     

 

Title                      

New Garin Reservoir and Pump Station Improvements: Authorization for the City Manager to Amend Professional Services Agreement for Additional Engineering Services During Construction                                                                                

End
RECOMMENDATION

 

Recommendation

That Council adopts the attached resolution amending the Professional Services Agreement with Kleinfelder, Inc., to increase the contract amount by $56,294 to a not to exceed amount of $356,294, for additional engineering services during construction related to the New Garin Reservoir and Pump Station Improvements Project.

 

End

SUMMARY

 

The City required the La Vista Development to build a new 0.75 million-gallon water storage reservoir and upgrade the existing Garin Pump Station. On September 15, 2015, the City and Kleinfelder, Inc. (Kleinfelder) entered into a Professional Services Agreement for Kleinfelder to provide engineering, design, and construction support services for the new reservoir and pump station improvements. Staff is requesting Council approval to increase the contract amount with Kleinfelder by $56,294 to a not to exceed amount of $356,294, to provide additional engineering services during construction.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                     Resolution