DATE: March 6, 2019
TO: Council Infrastructure Committee
FROM: Interim Director of Public Works
SUBJECT
Title
Fire Station 6 and Fire Training Center Design - Update
EndRECOMMENDATION
Recommendation
That the Committee reviews this report and comments on the current status of the Fire Station 6 and Fire Training Center Project.
End
SUMMARY
The design of Fire Station 6 and the Fire Training Center includes a full build out training center and includes a partnership with the Chabot-Las Positas Community College District. In preparation for the construction project, several pre-construction items are in progress. The project is currently in the construction document phase pending several review requirements. Staff anticipates that the design will be completed in late spring 2019, with construction anticipated to start in the Fall of 2019.
ATTACHMENTS
Attachment I Staff Report