DATE: April 1, 2019
TO: Council Economic Development Committee
FROM: Deputy City Manager
SUBJECT
Title
Review of a Site Plan Review from U-Haul to Demolish an Existing Historic Building and Construct Two New Industrial Buildings for a Corporate Facility on a 7.3-Acre Parcel Located at 4150 Point Eden Way
End
RECOMMENDATION
Recommendation
That the Council Economic Development Committee reviews and provides feedback on this proposed U-Haul facility to the applicant and staff.
End
SUMMARY
On February 25, 2019, U-Haul submitted a Site Plan Review application for a corporate U-Haul facility located at 4150 Point Eden Way. The project proposes two new concrete tilt-up buildings totaling 96,134 square feet in floor area, which would require the demolition of an existing historic building. The proposed facility would consist of a 56,848-square-foot flex warehouse building and a 40,786-square-foot corporate maintenance facility.
Levi Coulter from U-Haul (Applicant) will be present to discuss their proposal and answer questions from the committee.
ATTACHMENTS
Attachment I Staff Report
Attachment II Architectural Plans