File #: CONS 19-251   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 4/30/2019 Final action:
Subject: Authorization to Award a Construction Contract to Evans Brothers, Inc., in the amount of $246,300 for the Fire Station 6 and Fire Training Center Project-Abatement and Deconstruction and to Approve Addendum No. 1 to Clarify Plans and Specifications
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Summary of Bid Results

DATE:      April 30, 2019

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

 

Title                      

Authorization to Award a Construction Contract to Evans Brothers, Inc., in the amount of $246,300 for the Fire Station 6 and Fire Training Center Project-Abatement and Deconstruction and to Approve Addendum No. 1 to Clarify Plans and Specifications         

                              

End
RECOMMENDATION

Recommendation

 

That the Council adopts the attached resolution (Attachment II):

 

1.                     Approving Addendum No. 1, providing clarifications to the plans and specifications for the Fire Station 6 and Fire Training Center Project: Abatement and Deconstruction of Existing Buildings; and

 

2.                     Awarding the contract to Evans Brothers, Inc., in the amount of $246,300 and authorizing the expenditure of up to $425,000 for the total project, including contingencies.

 

SUMMARY

 

In order to construct the new Fire Station 6 and Fire Training Center, which is anticipated to begin later this year, the existing buildings at the current site will need to be deconstructed. Based on the materials sampling and testing conducted, hazardous materials abatement is required of these buildings prior to deconstruction. On April 2, 2019, seven (7) bids were received for the project. Staff recommends award of contract to the responsible low bidder, Evans Brothers, Inc., in the amount of $246,300.

 

ATTACHMENTS

Attachment I                     Staff Report

Attachment II                               Resolution

Attachment III              Summary of Bid Results