File #: PH 19-029   
Section: Public Hearing Status: Agenda Ready
Meeting Body: Planning Commission
Agenda Date: 5/9/2019 Final action:
Subject: Recommended FY 2020 - FY 2029 Capital Improvement Program
Attachments: 1. Attachment I Staff Report, 2. Attachment II Recommended FY 2020 - FY 2029 CIP

DATE:      May 9, 2019

 

TO:           Planning Commission

 

FROM:     Planning Manager

 

SUBJECT                     

Title                      

 

Recommended FY 2020 - FY 2029 Capital Improvement Program                                                             

 

End
RECOMMENDATION

Recommendation

 

That the Planning Commission finds that the Recommended FY 2020 - FY 2029 Capital Improvement Program is consistent with the Hayward 2040 General Plan.

End

 

SUMMARY

 

The City’s Capital Improvement Program (CIP) is a planning document for the upcoming ten-year period. It supports the City Council’s priorities of Safe, Clean, Green, and Thrive, and the three Strategic Initiatives - Complete Communities, Complete Streets, and the Tennyson Corridor.  The CIP planning document (Attachment II) includes budget recommendations that contain revenue and expenditure estimates for capital projects.

 

The proposed CIP budget includes approximately $148 million in FY 2020 and an estimated $520 million in the next ten years. Given that Hayward is a full-service city, the CIP covers a wide range of projects, including an Airport, Roadways and Streets, Transportation, Buildings, Water System, Groundwater, Wastewater System with a Water Pollution Control Facility, Recycled Water, and Renewable Energy.  The CIP likewise includes projects and purchases for Facilities, Information Technology, and Fleet vehicles. As in past years, the document also includes Identified and Unfunded Capital Needs, which currently total over $400 million.

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Recommended FY2020-2029 CIP Budget