Subject: 21st Century Library and Community Learning Center and Heritage Plaza: Public Contract Code § 4107 Hearing Regarding Removal and Substitution of the Electrical Subcontractor, Collins Electrical Company, Inc (Report from Public Works Director Ameri and City Attorney Lawson) (Continued from July 16, 2019)
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:                     July 9, 2019

 

TO:                     Mayor and City Council

 

FROM:                     Director of Public Works

                     City Attorney

 

SUBJECT                     

 

21st Century Library and Community Learning Center and Heritage Plaza: Public Contract Code § 4107 Hearing Regarding Removal and Substitution of the Electrical Subcontractor, Collins Electrical Company, Inc.

 

RECOMMENDATION

 

That the Council, after conducting a hearing, considers and approves a resolution for the removal of Collins Electrical Company, Inc. as the electrical subcontractor on the 21st Century Library project and authorizes the City Manager to approve a substitute subcontractor to perform the electrical work pursuant to Public Contract Code § 4107.

 

SUMMARY

 

On July 2, 2019, the City transmitted a letter to T. B. Penick & Sons, Inc. (TBP) requesting that they remove Collins Electrical Company, Inc., (Collins) from the project and identify a responsible electrical contractor for submittal as a substitute. The request is based on disruptive actions and project delays attributed to Collins.  The City sent a notification to Collins regarding its request that TBP remove them as a subcontractor on this project. 

 

The terms of the construction contract for the library project require the contractor to immediately remove a subcontractor who fails to satisfactorily prosecute the work, upon request by the City.   The Public Contract Code requires a public hearing by the awarding authority whenever a subcontractor objects to being removed from a project and replaced with a substitute. 

 